Construction Updates
Phone: 719.276.5291
Email: 2Astreets@canoncity.org
2A Project Construction Map (2017-2019)
Construction Update 9/25/2018
- Traffic on Central Ave will have to stop at Raynolds Ave. (see map)
- Parents dropping off and picking up children at Harrison School and MVCKS will be re-routed to Raynolds Ave connecting temporarily to South Street. (see map)
2A Street Improvement Project 2018 Status
City Council has chosen this year to return to the traditional Design/Bid/Build process (Resolution 5-2018) as well as complete the work in smaller projects, making it more competitive for local contractors.
This change in process has caused a small delay and change in scope for 2018.
This year the following streets will get reconstructed:
- Field Ave – Central Ave to High Street
- Park Ave – 9th Street to 12th Street
Construction should take place late summer to early fall.
Construction Update 5/2/2018
Kiewit construction crews will be completing punch list items from the 2017 2A Street Improvement Project beginning this spring. Canon City residents should expect to see intermittent temporary lane restrictions as punch list items are completed. Remaining work includes infrared heat treat at water valves, finishing manholes and joints, touch-up shoulder work, and landscaping. Completing required punch list items will begin mid-May and wrap up in late summer.
2017 Construction
On April 17, 2017, the City Council awarded Kiewit Infrastructure the Design/Build Street Improvement Project (Referendum #2A).
2017 Priority Road Construction Maps
Detailed City Map - 2A streets
11x13 map - 2A streets
Weekly Construction Update Sheet
• June 19 • June 26 • July 3 • July 10 • July 17 • July 24
• July 31 • Aug 7 • Aug 21 • Aug 28 • Sept 4 • Sept 11
• Sept 18 • Sept 25 • Oct 2 • Oct 9 • Oct 16 • Oct 23
• Oct 30 • Nov 6 • Nov 13 • Nov 20 • Nov 27 • Dec 4
• Dec 11 • Dec 18
Kiewit Presentation and Update to City Council on December 4, 2017
Slide Presentation
Handout