The City of Cañon City has two optional ways of determining building permit fees: the square foot construction costs per Building Valuation Data or Construction Contract for Actual Cost per Ordinance No. 7, Series of 2013. Cañon City’s use tax is 2%. An example of calculating Permit Fees is as follows. Click on highlighted text for more information: 

Example of Building Valuation Data:

Group = R-3 (Residential Home)

Type of Construction = VB

Finished Area = 2000 S.F. x 112.65 = 225,300.00

Unfinished Basement = 1000 S.F. x 15.00 = 15,000.00

Garage = 800 S.F. x 43.33 = 34,664.00

Total Valuation = 225,300.00 + 15,000.00 + 43,664.00 = 274,964.00

Permit Fee = 274,965.00 x .00998 (City of Cañon City Permit Fee Multiplier) = 2,744.14

Use Tax = 274,964.00 x 50% = 137,482.00.00 x 2.0% = 2,749.64

Mechanical Fee = 60.75 (See Schedule for Mechanical Fees)

Total Permit Fees = 5,554.53

Example of Actual Construction Contract:

Contract = 180,000.00 x .00998 = 1,796.40 (Permit Fee)

Use Tax = S.F. cost 274,964.00 (see above for the total valuation example) x 50% = 137,482.00 x 2.0% = 2,749.64

Mechanical Fee = 60.75 (See Schedule for Mechanical Fees)

Total Permit Fees = 4,606.79

Other Fees Which May Apply:
Electrical Permit (State of Colorado)
Plumbing Permit (State of Colorado)
Fire Impact Fee (Cañon City collects this fee for the Fire Department)

For any questions please feel free to contact the Building Department at 719-276-5292.